Welcome to CdM High School HS ASB/Activities Staff/Teachers CdM High School World Languages Contact Us Attendance Policy AGS Cheer and Song Page Mission and Goals PAMA New to High School IMPORTANT INFORMATION Theatre
Welcome to CdM Middle School MS ASB/Activities Staff/MS Activities Eligibility Middle School Athletics Middle School Languages MS Principal's Message New to Middle School Important Information Cheer - Middle School Renaissance MS Elective Forms & Applications Boys Volleyball Schedule Girls Basketball Schedule Girls Volleyball Schedule Boys Basketball Schedule Boys Soccer Girls Soccer
Academics High School Athletics Counseling LRC - College Guidance Signature Academies
PTA Alumni Backstage and Performing Artists Company Board of Education Boosters CdM Foundation Newport-Mesa Schools Foundation SCO Handbook
Calendar and Bell Schedule Contact Us District Information Handbook Nurses Office New Student Info for 2019-2020 Lunch Menu/Nutrition Maps Registration Wireless Student Setup Library Plug-ins Common Core Math Daily Announcements ASB/Student Store CdM Staff Resources Professional Development School News School Profile - 2018-2019 Trident TV

News Item: Homepage

Facilities Project Update - July 2018

Heating, Ventilation, Air Conditioning (HVAC) – College Park, Davis and Pomona Elementary

Contractor: AireMasters

Elementary School Campus Under Construction

Completed protection of all spaces, safety barriers, and scaffold access. Continuing demolition of old heating equipment to make space for new equipment. Received all interior equipment and started interior ductwork. Upcoming activities include prepping concrete pads and selective roof demolition.


Heating, Ventilation, Air Conditioning (HVAC) – Kaiser and Woodland Elementary

Contractor: LA Air

Elementary School Office Under Construction

Completed protection of all spaces, safety barriers, and scaffold access. Continuing demolition of old heating equipment to make space for new equipment. Started concrete pad layout for new ground mounted HVAC units. Upcoming activities include pouring concrete pads and receiving HVAC equipment.


Admin and Fence – Mariners and Newport Heights Elementary

Contractor: JRH Construction

Elementary School Campus Under Construction

Completed abatement of entire office building. Continued demolition of interior walls and in-wall plumbing. Commenced low voltage rework. Set reinforcing bars and formwork for curb and ramp in parking lot. Removed landscaping in front of new storefront entry. Upcoming activities include pouring concrete for ramp and reframing interior walls.


Heating, Ventilation, Air Conditioning (HVAC) – Wilson Elementary

Contractor: NKS Mechanical

Elementary School Campus Under Construction

Completed abatement of entire office building. Continued demolition of interior walls and in-wall plumbing. Continued to run electrical conduit in classroom buildings. Started grubbing for new housekeeping pads for new condensing unit. Completed demotion of concrete bus drop off. Upcoming activities include reframing interior walls in office building, setting steel for housekeeping pads and pouring concrete.

Posted by: Adriana Angulo, District Admin, Newport Mesa Unified School District Published:7/11/18